Dutch electricity queue climbs past 15,000 firms
Nearly 15,500 companies and organisations in the Netherlands now wait for power connections as grid congestion continues to spread.
Why it matters: The overstretched grid delays housing developments and business sustainability plans, inflicting an estimated €10 billion to €35 billion in annual economic damage, according to a 2024 Boston Consultancy Group report.
By the numbers:
- The queue expanded by more than 300 applicants in the first half of 2026, reported Netbeheer Nederland (the association of Dutch grid operators).
- Grid managers expect network enlargement will cost €235 billion for items like cables and transformer stations.
- Variable electricity rates planned for 2029 could free up capacity for 700,000 new dwellings, advisory firm Berenschot calculated.
The alternative view: Energy transition professor Jan Rotmans argued intelligent planning could halve expansion spending, citing an Arnhem project where network operator Alliander connects 7,000 homes using a connection three times smaller than usual by flattening peak usage.
What is next: Minister Boekholt-O'Sullivan wants grid-aware building methods to become standard from 2028, the same year Utrecht officials hope to resume connecting applicants following regional connection freezes.